Project Updates:
- A road closure in Lake Whitney Ln is being coordinated. Further details are coming up later this month.
· NTMWD contractor completed the North and South bore pits and will be working on the tunnel until the pipe is delivered in mid-June.
· Road closures in Travis Dr., Lake Travis Dr., and E Round Rock are anticipated in the summer. These closures will be phased and communicated to minimize impacts on traffic.
· Utility investigations are still ongoing.