Apr 07

Angel Parkway Construction Update #2

  • Project Updates:
  • NTMWD is coordinating with Coserv as they are also relocating in this area.  
  • NTMWD contractor anticipates starting construction of a bore pit North of Lake Travis Dr., next week. This will not impact traffic, trash collection, or bus routes. 
  • NTMWD contractor anticipates demolishing the brick wall next week once Coserv completes their work.
  • NTMWD contractor anticipates constructing a bore pit next to the interception of Lake Whitney Lane with Lake Texoma Circle the week of April 18. Road closure in Lake Whitney Lane is anticipated for 2-3 days. Once the bore pit is complete, one lane is anticipated to remain open to allow traffic in both directions by Thursday, which will allow for the normal operation of trash collection services. NTMWD is also coordinating with Allen ISD and has communicated the anticipated road closure. 

Apr 07

Angel Parkway Construction Update #1

From the City of Allen:

Mar 24

Angel Parkway Utility Work – East Wall Demolition

You may have noticed that the North Texas Municipal Water District (NTMWD) is doing utility work along our wall. They will be placing an 8 inch line in preparation for the Angel Parkway widening project. As a result of this work, they will be demolishing our current wall and it will be gone for the length of the project. Plans have been somewhat fluid as the project has developed. The HOA was originally told that demolition would not occur until this summer. However, we have just been informed that demolition has been advanced to Thursday, March 31st. Once demolition starts there may be some road closures in the neighborhood.


Going forward we plan to keep you updated both here and via the HOA Facebook page. More details will be provided as soon as we have them.